In YTL Power Services Pasir Gudang, 2 units / blocks of Siemens V94.2 gas turbines, single shaft, single casing and heavy duty design were installed. The V94.2 gas turbines are driving air cooled generators which have a rated ISO-power of 150 MW.
The 25 days duration of gas turbine unit 11 major overhaul start since 15 July t0 8 Aug 2009. Here I will posts some of the interesting photos up!
Huh, this single blade can buy me one car!
4 stages of turbine rotors
16 stages of compressor rotors
The whole rotor was in up-ending position to remove every stages of rotor blades
Stages of compressor rotors
Removal of blades from rotors and vanes (stators)
Flame tube to be refurbished
Coating of vanes
Abradable coating of compressor carrier
After assembled back into tie rod, it is time for installation!
4 stages of turbine rotors
16 stages of compressor rotors
The whole rotor was in up-ending position to remove every stages of rotor blades
Stages of compressor rotors
Removal of blades from rotors and vanes (stators)
Flame tube to be refurbished
Coating of vanes
Abradable coating of compressor carrier
After assembled back into tie rod, it is time for installation!
This overhaul give me plenty of interesting experience and enhance my knowledge on gas turbine. Thank you to my company for giving me this opportunity. ^_^
1 comments:
Hi Vincent,
We might have some job opportunities involving overhaul work with Siemens V-frame Turbines.
If you're interested please email me at mwalsh@shanahaneng.ie.
Regards,
Mark Walsh
Sourcing Specialst at Shanahan Engineering
Post a Comment